ПраймПресс - интернет-ресурс для бизнеса
  • Новости
  • Экономика
  • Финансы
  • Компании
  • Экспертиза
  • Стиль жизни
  • Реклама
Все новости
Новости экономики

BelNPP to restart first unit next week after equipment failure

<p> MINSK, Nov 13 - PrimePress. The repeated launch of the first power unit of the Belarusian nuclear power plant (BelNPP, Astravyets, Grodno Oblast) is scheduled for next week. </p> <p>   </p> <p> The shutdown of the first unit occurred on November 8 due to the breakdown of electrical equipment, said Atomstroyexport Vice-President Vitaly Polyanin. (Russia’s Atomstroyexport is the general contractor for the Astravyets nuclear project). </p> <p>   </p> <p> “It was previously revealed that the voltage transformers failed from the measuring circuit of the block transformer protection as a result of internal short circuit. The equipment is made in Italy; now we are changing the transformers for Russian-made ones from Rosenergoatom’s reserves.” Polyanin said in an interview published by the Kommersant newspaper on November 13. </p> <p>   </p> <p> In his words, they plan to connect the unit to the grid early next week after equipment installation and tests. </p> <p>   </p> <p> The incident at the BelNPP “is not a critical case, but an absolutely routine situation for this stage,” Polyanin said. </p> <p>   </p> <p> “Such cases have already occurred in the history of the Russian nuclear power industry. Much depends on the quality of manufacture of this type of transformers, which are operated in fairly harsh conditions. But this is our task at this stage to identify all the bottlenecks before the unit is put into commercial operation,” Polyanin said. </p> <p>   </p> <p> He also noted that the radiation background at the site is normal, “according to the IAEA international scale, this incident is zero”. “At this stage of commissioning the unit, electricity generation does not play a decisive role, the main thing is to check the operation of equipment and systems in all operating modes of the unit,” said Polyanin. </p> <p>   </p> <p> As previously reported, the first power unit of the BelNPP was integrated into the unified power grid of Belarus on November 3. On November 7, the first unit reached the capacity of 400 MW, and on November 8 the production of electricity was suspended. The Energy Ministry of Belarus confirmed the fact of temporary interruption of electricity supply from the Belarusian NPP. </p> <p>   </p> <p> Belarus’ first nuclear power plant in Ostrovets (a town in the Grodno Oblast also referred to as Astravyets) will have two units with a combined capacity of up to 2,400 megawatts. The AES-2006 Russian standard design of (generation 3+) was chosen for its construction. Rosatom’s division Atomstroyexport acts as the general contractor for the NPP construction. The Belarusian Nuclear Power Plant RUE is the project customer and the future operator of the NPP. The first power unit was launched on November 3, 2020. It is expected to be put into commercial operation in February 2021; the second unit – in May 2022. End </p>

2020-11-14

Primepress

Primepress ltd
220074
Belarus
Minsk
+37529184 06 73
primepress.by

BelNPP to restart first unit next week after equipment failure

MINSK, Nov 13 - PrimePress. The repeated launch of the first power unit of the Belarusian nuclear power plant (BelNPP, Astravyets, Grodno Oblast) is scheduled for next week.

 

The shutdown of the first unit occurred on November 8 due to the breakdown of electrical equipment, said Atomstroyexport Vice-President Vitaly Polyanin. (Russia’s Atomstroyexport is the general contractor for the Astravyets nuclear project).

 

“It was previously revealed that the voltage transformers failed from the measuring circuit of the block transformer protection as a result of internal short circuit. The equipment is made in Italy; now we are changing the transformers for Russian-made ones from Rosenergoatom’s reserves.” Polyanin said in an interview published by the Kommersant newspaper on November 13.

 

In his words, they plan to connect the unit to the grid early next week after equipment installation and tests.

 

The incident at the BelNPP “is not a critical case, but an absolutely routine situation for this stage,” Polyanin said.

 

“Such cases have already occurred in the history of the Russian nuclear power industry. Much depends on the quality of manufacture of this type of transformers, which are operated in fairly harsh conditions. But this is our task at this stage to identify all the bottlenecks before the unit is put into commercial operation,” Polyanin said.

 

He also noted that the radiation background at the site is normal, “according to the IAEA international scale, this incident is zero”. “At this stage of commissioning the unit, electricity generation does not play a decisive role, the main thing is to check the operation of equipment and systems in all operating modes of the unit,” said Polyanin.

 

As previously reported, the first power unit of the BelNPP was integrated into the unified power grid of Belarus on November 3. On November 7, the first unit reached the capacity of 400 MW, and on November 8 the production of electricity was suspended. The Energy Ministry of Belarus confirmed the fact of temporary interruption of electricity supply from the Belarusian NPP.

 

Belarus’ first nuclear power plant in Ostrovets (a town in the Grodno Oblast also referred to as Astravyets) will have two units with a combined capacity of up to 2,400 megawatts. The AES-2006 Russian standard design of (generation 3+) was chosen for its construction. Rosatom’s division Atomstroyexport acts as the general contractor for the NPP construction. The Belarusian Nuclear Power Plant RUE is the project customer and the future operator of the NPP. The first power unit was launched on November 3, 2020. It is expected to be put into commercial operation in February 2021; the second unit – in May 2022. End

2020-11-14

Возврат к списку

Обзоры
«Прайм Эксперт» №44: Greatport на треть увеличит терминальную мощность Беларуси, годовая инфляция ускорилась до 4,7%
В новом выпуске еженедельного бюллетеня ПраймПресс «Прайм Эксперт» №44 (523) от 13 ноября 2026 г – терминал Greatport, который на 30% увеличит терминальную мощность Беларуси, и ускорение годовой инфляции до 4,7% с 4,6% за счет услуг. Мы делаем бюллетень для тех, кто в банках и крупных компаниях принимает стратегические решения, работает над выходом на внешние рынки, оценивает риски, планирует бюджеты и цены.
16 Ноября 2026
«Прайм Эксперт» №43: Кредиты становятся дешевле, нагрузка на бизнес растет
«Прайм Эксперт» каждую неделю собирает в одном выпуске ключевые решения властей и регуляторов, данные статистики и аналитику, нужные бизнесу для работы в Беларуси и с белорусскими партнерами. Это помогает быстрее оценивать изменения, точнее выстраивать платежи и поставки и принимать решения на основе проверенной информации.
6 Ноября 2026
«Прайм Эксперт» №42 от 30 октября 2026 г: белорусская экономика вышла на плато
30 октября мы выпустили свежий мониторинг экономики Беларуси «Прайм Эксперт» (№42). В выпуске собраны события и данные за последнюю неделю, и каждый ключевой сюжет мы не только проверяем и усиливаем контекстом, но и разбираем.
2 Ноября 2026
Наши продукты: ежедневный выпуск «Прайм Бизнес» и еженедельный мониторинг экономики «Прайм Эксперт»

Компания «ПраймПресс» – поставщик деловой информации и аналитики о Беларуси для крупных и средних компаний, банков и регуляторов. Мы быстро и профессионально находим, проверяем, отбираем и объясняем решения властей, новые правила, изменения в расчетах и на отраслевых рынках. Наш сайт показывает, что произошло. Подписка помогает понять, что это значит: в ней полные версии новостей, справки и аналитика ПраймПресс. Предлагаем бесплатную тестовую рассылку на 14 дней. 



28 Октября 2026
Потребительский рынок Беларуси: товарооборот вырос на 8,4%, драйвером стали маркетплейсы и кредиты. Платный обзор
Компания ПраймПресс подготовила новый выпуск ежемесячного аналитического обзора «Потребительский рынок Республики Беларусь. Тенденции и прогнозы» за январь-август 2026 г. Обзор будет полезен руководителям торговых сетей, производителям и поставщикам потребительских товаров, импортерам и дистрибьюторам, банкам, работающим с розничным кредитованием, а также маркетологам и инвесторам. По нему можно оценить спрос, спланировать ассортимент и закупки, выбрать регионы для развития и учесть изменения в регулировании торговли.
28 Октября 2026
Все обзоры
ПраймПресс - интернет-ресурс для бизнеса
  • О нас
  • Услуги
  • Реклама
  • Договор оферты
  • Политика перепечатки и распространения информации
  • Контакты
Общество с ограниченной ответственностью «ПраймПресс» (ООО «ПраймПресс»);
Юридический адрес: 220074, Республика Беларусь, г.Минск ул.Харьковская,90, пом.16;
Свидетельство о государственной регистрации юридического лица выдано Минским горисполкомом 15 апреля 2016 г. Регистрационный номер 192636246
Оказываем услуги юридическим лицам, физическим лицам и ИП, не являемся интернет-магазином
Нет лицензирования
9.00-18.00, в будние дни
+375 (29) 1840673
info@primepress.by
                           

Visa MastercardSecure Mastercard Belcart E-POS

Подпишитесь на наш Telegram

Актуальная информация и свежие новости экономики и бизнеса!

Подписаться на канал